The Redevelopment
August 2006
- The £2m Modernisation commences.
- Work to the new Seafood Restaurant begins.
- Old workshops will be demolished and building for the new work shops commences.
December 2006
- New workshops will be completed. The workshops will house equipment for the ground staff team.
- The new Seafood Restaurant will be expanded to a 50 cover self service restaurant.
July 2007
- The new 150 cover Raceday Restaurant will be opened to the public. It will be available to hire for non-racing events.
November 2007
- The new Weighing Room will be opened. Jockeys will move into their new changing facilities located on the ground floor of the Paddock Building.
- The old Changing and Weighing Rooms will be demolished to make way for the Marquee Lawn.
April 2008
- The Marquee Lawn will be open for business.

|